Implement Earned Value Management (EVM)
EVM is the gold standard for project cost control. Track CPI and SPI weekly. A CPI below 0.9 is an early warning signal — don't wait until it hits 0.7 to act. PMI research shows projects that implement EVM are 3x more likely to finish within 10% of budget.
Implementation Steps
- 1Define Work Breakdown Structure (WBS) to 100% scope
- 2Assign budgets to each WBS element
- 3Track Earned Value (% complete × BAC) weekly
- 4Calculate CPI = EV ÷ AC every reporting cycle
- 5Forecast EAC = BAC ÷ CPI and report to sponsors
- 6Trigger recovery plan when CPI drops below 0.9
Tools & Methods
- Microsoft Project
- Primavera P6
- Deltek Cobra
- Earned Value Spreadsheet (free)