Crossrail (Elizabeth Line): The 4-Year Delay

Crossrail was due to open in December 2018 at a cost of 14.8bn GBP. It opened in May 2022. In July 2021 the NAO put the forecast cost at 18.9bn GBP, a 28% nominal increase on the 2010 budget, within an 18.8bn GBP funding package. The NAO published two scathing reviews (2019 and 2022) identifying signalling and systems integration as the central failure.

18.9B GBP
forecast cost (NAO, July 2021)
3.5 years
behind schedule
+28%
nominal increase on the 2010 budget (NAO)

What went wrong, per the NAO

The 2019 NAO report identified three structural failures:

  • Signalling integration was scheduled in parallel with civil works finalisation. The three signalling systems (Network Rail mainline, Crossrail central tunnel, and Heathrow approach) had to be integrated by 2018. They could not be, because the central tunnel civils were not complete in time.
  • The single-systems-integrator model was abandoned mid-project. Crossrail Ltd took on the role itself, without the capability to do so. The 2022 NAO report singled this out as the "most significant strategic error".
  • Cost-to-complete forecasting was missing for the systems work. Civils were tracked in detail, but systems integration cost had no equivalent earned-value baseline. Slippage was invisible to the board until it had compounded into a year-long delay.

Sources

Related

Didn't find your answer?

Ask us. A real person reads every question and we answer the ones we can, with sources. If your question would help other readers, we may publish an anonymised version, with your permission. General reference, not financial advice.

Ask a question

questions@budgetoverrun.com

Updated 2026-10-08